Introduction

In Spindle Document Distribution Tools, Document Operations are executed in the order they are listed, which is the order in which they were created. You may find that you need to re-order the operations.

Applies to

  • Spindle Professional 2009
  • Spindle Professional 2012
  • Spindle Professional v6
  • Spindle Document Distribution v7
  • Spindle Document Distribution v8

Process

In the image below, we can see that the document operations were created in the order 1, 3, 2, but we want them to run in order 1, 2, 3:

To change the order we can select operation 3 and create a copy of it. The copy will be placed at the bottom of the list:

Which gives us



With the copy at the end of the list, we can now delete the original Operation 3:


And finally rename Copy of 3 to simply 3:

Leaving us with :





Knowledge Base Article Details

Related ProductSpindle Professional, Spindle Document Distribution
Ref NumberKBA-01-02-033
Document Date05/09/2019
Original AuthorVince Hodgson
Document Versionv1.0
Last updated 05/09/2019
Update Author Vince Hodgson